|
Meeting No. |
Date |
Main
Topics |
|
2008-10 |
29-AUG-08 |
Hardware Baseline:
Engineering change control/Engineering specs -
Hardware
commissioning:
Status of the cool down - Results of the power tests -
Results from the latest injection test -
Planning to September 10th - Objectives for September 10th. |
|
2008-09 |
01-AUG-08 |
General
Information - Hardware Baseline:
Engineering change control/Engineering specs -
Electrical infrastructure -
Hardware
commissioning:
Status of the cool down - Progress of Powering Tests - Preparation for the Injection Test -
DSO tests. |
|
2008-08 |
04-JUL-08 |
General
Information - Hardware Baseline:
Engineering change control/Engineering specs -
Hardware
commissioning:
LHC cryogenics
situation - Status of ongoing power tests - Operations
testing in Sector 56 -
DSO tests. |
|
2008-07 |
06-JUN-08 |
General
Information - Hardware Baseline:
Engineering change control/Engineering specs -
Cool down of the machine
-
Power tests
-
Training campaign of the
dipole magnets. |
|
2008-06 |
21-MAY-08 |
Status
of the cooldown - Status of
the power tests - Procedures for removal of material from the
LHC - Plans for minimizing single events upsets in the LHC -
Actions ongoing for shielding sensitive electronics - Situation
with the beam dump dilution kickers of beam 2. |
|
2008-05 |
9-MAY-08 |
General
Information - Hardware Baseline:
Engineering change control/Engineering specs -
Tour of the Ring:
Status of cool down
- Status of repairs and consolidation - Status and plans for
power tests -
Humidity on Sector 34. |
|
2008-04 |
11-APR-08 |
General
Information - Hardware Baseline:
Engineering change control/Engineering specs -
Tour of the Ring:
Status of cool down
- Status of repairs and consolidation - Status and plans for
power tests - Radiation issues on electronics. |
|
2008-03 |
14-MAR-08 |
General Information - Hardware Baseline:
Engineering change control/Engineering specs -
Tour of the Ring:
Cryogenics situation
- Consolidation activities -
Preparations
for powering
-
Summary of
Sector 45 Review. |
|
2008-02 |
15-FEB-08 |
General Information - Hardware Baseline:
Engineering change control/Engineering specs - Hardware Commissioning:
LHC
cryogenics situation -
Status of
powering tests
-
Consolidation
work - Recent changes affecting the schedule. |
|
2008-01 |
18-JAN-08 |
General Information - Hardware Baseline:
Engineering change control/Engineering specs -
Access control system reception tests - Hardware Commissioning:
LHC
cryogenics situation -
Power tests in Sector 4-5 -
Mid-term plan. |