ICC Meetings Minutes 2007

LHC Homepage

     

Meeting No. Date Main Topics
2007-11 14-DEC-07

General Information - Hardware Baseline: Engineering change control/Engineering specs - Assembly: The LHC arc interconnect programm - Leaks in Sector 8-1 - Hardware Commissioning:  Cryogenic activities around the machine - Power tests - RF system start-up - Alignment of LHCb and ALICE compensator magnets - Update on the progress.

2007-10 16-NOV-07

General Information - Hardware Baseline: Engineering change control/Engineering specs - Assembly: Bellows of the SSS level gauges in Sector 1-2 - Leaks in Sector 7-8 - Hardware Commissioning:  Cryogenic activities around the machine - Radiation issues during CNGS operation - Correlation with simulations - Update on the progress.

2007-09 19-OCT-07

General Information - Hardware Baseline: Engineering change control/Engineering specs - Assembly: Status of Sector 78 status - Status of Sector 81 exchange of SSS, leak tests - Hardware Commissioning:  Status of Sector 45 cool down - Status of Sector 56 preparation for flushing - Status of Sector 67 preparation for pressure test - Update on DSLC installation - Update on water-cooled cables - Update PIMs - Update on the progress - Cooling of the thermal screens in Sector 12 - Situation with the TI2 beam tests.

2007-08 21-SEP-07

General information - Hardware baseline: Engineering change control/Engineering specs - Hardware commissioning: Sector 4-5 - Sector 7-8 - Sector 8-1 - Situation with the Plug in Modules - Progress and Master Schedule.

2007-07 17-AUG-07

General information - Hardware baseline: Engineering change control/Engineering specs - Cool down of Sector 4-5 - Inner Triplet installation and consolidation of Sector 7-8 - Situation in Sector 8-1 - Master Schedule and progress.

2007-06 22-JUN-07

General information - Hardware baseline: Engineering change control/Engineering specs - Triplet repair - Planning and installation: Status of LHC installation - Version 4.0 of the General Coordination Schedule - Hardware commissioning: Status of the cryogenics in Sectors 7-8 and 4-5 - ELQA in Sector 7-8 - Progress with powering tests in Sector 7-8.

2007-05 25-MAY-07

General information - Hardware baseline: Engineering change control/Engineering specs - Triplet repair - Status of Sector 4-5 - Status of the DSL - Planning and installation: Status of LHC installation and new installation schedule - Hardware commissioning: Progress with cool down of Sector 7-8 - Status of the powering tests.

2007-04 27-APR-07

General information - Report from triplet review - Warm vacuum systems - Hardware baseline: Engineering change control/Engineering specs - Planning and installation: Status of LHC installation - Options for commissioning Sector 4-5 - Hardware commissioning: Progress with cool down of Sector 7-8 - Preparation for and progress with power tests.

2007-03 30-MAR-07

General information - Hardware commissioning: Latest on the Triplet Magnets - Progress with cool down of Sector 7-8 - Status of the RF systems - Status on the Injection System and Warm Magnets at Point 8 - Progress with Electrical Quality Assurance at cold - News - Hardware baseline: Engineering change control/Engineering specs - Status of LHC installation.

2007-02 02-MAR-07

General information - Hardware baseline: Engineering change control/Engineering specs - Planning and installation: Status of installation - Inner triplet repair - Implications for planning - Hardware commissioning: News - Progress with cool down of Sector 7-8 - Preparations for powering Sector 7-8 - Collimator status.

2007-01 02-FEB-07

Introduction to the ICC - Hardware baseline: Engineering change control/Engineering specs - Planning and installation: Status of inner triplet repair - Status of installation - Hardware commissioning - Cool down of Sector 7-8.


Webmaster

Last update: 19/12/07